Architecture project management: track team time against stage fees and bill clients

Turn each stage fee into a budget of hours, compare hours used with work done every week, and bill on the agreed trigger. A worked tracker that spots an overrun while you can still act.

Last updated November 6, 2026

Architecture project management, on the money side, means turning each stage fee into a budget of hours, logging the team's time against that stage every week, comparing hours used with work done, and invoicing when the agreed trigger arrives. That comparison catches an overrun while you can still do something about it.

This guide is about keeping a fixed fee profitable while the project runs. Design coordination and the statutory side are a different subject, and the RIBA Plan of Work overview is the place for those.

How do you turn a stage fee into a budget of hours?

Turn a stage fee into a budget of hours by holding back a contingency and dividing what remains by your blended rate. Here's an invented example, with a 10% contingency and a blended rate of £85 an hour:

Stage Fee Less 10% held back Budget hours at £85
2 Concept Design £6,000 £5,400 63
3 Spatial Coordination £8,400 £7,560 88
4 Technical Design £11,600 £10,440 122

Hours are rounded down. If you wrote the fee proposal from past hours, the budget should be close to what you estimated then. Tell the team the number. A budget only the director knows about can't influence anyone's Tuesday.

How do you track team time against a stage fee?

Track team time against a stage fee by having everyone log hours to the project and the stage at least weekly, then comparing the total with an honest estimate of how much of the stage is done.

Three rules make the numbers usable:

  1. Log to the stage, not only the project. "Smith House: 6 hours" can't tell you which fee it came out of.
  2. Log additional services separately. They're paid on top, so hours on them shouldn't eat the stage budget. See additional services.
  3. Estimate progress from what's been produced. Count the drawings and tasks left, and ignore the hours used. Otherwise the check proves nothing.

The tracker itself can be one row per stage. Here it is for the same invented job, four weeks into Stage 3:

Stage Budget hours Hours used Budget used Work done Projected total Over or under
2 Concept Design 63 58 92% 100% 58 5 under
3 Spatial Coordination 88 62 70% 50% 124 36 over
4 Technical Design 122 6 5% 5% 120 2 under

Projected total is hours used divided by work done, so Stage 3 reads 62 ÷ 50% = 124. That's 36 hours over budget, or £3,060 at £85, more than the £840 contingency held back on that stage. You now know that with half the stage still to run. The guide to budget hours vs actual hours goes deeper into reading these numbers on a single fixed-fee job.

What do you do when a stage is running over?

When a stage is running over, find the cause before you decide anything, because each cause has a different fix.

Cause What to do
The client changed something Stop and agree it as an additional service
The design hasn't settled Get a director to make the decision that's holding it up
The job is too senior or too junior for the people on it Change who's doing what, since the blended rate moves too
More coordination with consultants than you assumed Check your assumptions in the appointment, and raise it if they've been broken
The estimate was too low Finish the stage, take the loss and correct your numbers for the next proposal

Don't quietly borrow hours from Stage 4. The next stage's budget is what pays for the next stage, and the shortfall just arrives later with less time to fix it.

When should you bill a stage: at the end, monthly or by instalment?

Bill a stage at the point your appointment says, and if it doesn't say, monthly by progress is usually the best option on stages lasting more than a few weeks.

Pattern Suits Watch out for
At the end of each stage Short stages, small jobs You fund the whole stage, and a stalled project leaves it unbilled
Monthly, by share of work done Stages 2 to 4 on larger jobs Needs a progress figure the client accepts
Equal monthly instalments Stage 5, over the contract period State what happens if the build overruns

For monthly billing, invoice the stage's progress to date less what you've already billed. On the invented job, Stage 3 at 50% earns £4,200 of the £8,400 fee. If £2,800 has gone out already, this month's invoice is £1,400 plus VAT. Hours used don't come into it. The guides to RIBA stage fees and progress billing cover the wording and how to set up the stages.

Where do projects like this usually go wrong?

Fixed-fee architecture projects usually go wrong through small habits that hide the numbers until it's too late.

  • Time typed in weeks later. Nobody remembers, so everything lands on whichever project is loudest.
  • Reviewing only at stage end. By then the hours are spent and the client has signed off.
  • Treating hours used as progress. A stage that's 70% through its hours isn't 70% done.
  • No owner. One named person should review each project's numbers each week, even in a small practice.
  • Unlogged "quick favours" for the client. Each one is small. Together they're often the overrun.

Running stages and invoices in ERPFlow

ERPFlow doesn't have a timer or timesheets today. Time tracking, including converting tracked time into invoices, is coming soon. ERPFlow has no stage budgets, staff rates or per-project profitability, and expenses aren't linked to projects, so the tracker above stays in a spreadsheet. Here is what ERPFlow does cover:

  • The board. A board in Projects per job, linked to its customer, with columns named after your stages. The signed appointment can sit in the board's own attachments. See how projects work. Boards are unlimited on every plan, and the Free plan caps cards at 10.
  • The work. A card per deliverable or stage, with assignees, a deadline, files, comments and time spent typed in as hours and minutes. Totals add up per project and per customer, and the card export gives you the time per card for your tracker.
  • The fee. A quote with one line per stage. A service can hold your hourly rate for additional work.
  • The stage invoice. This is an ordinary invoice with an edited line. Convert the quote, delete the other stages, and set the line to this period's amount, such as "RIBA Stage 3: 50% of £8,400, less £2,800 invoiced" at £1,400. The draft keeps the quote's project, and the quote's Linked documents lists every invoice made from it, so you can see what's been billed so far.

FAQ

Running architecture projects: common questions

Didn't find your answer here? We're happy to help.

Contact us
How often should an architecture practice compare hours with the stage fee?
Weekly while a stage is active. An architecture practice that compares hours with the stage fee only at the end of a stage finds out about an overrun when nothing can be done. A short weekly review of hours used against work done takes a few minutes per project.
Should an architect invoice a stage by the hours used so far?
No, not on a fixed fee. A fixed stage fee is earned by progress, so invoice the share of the work completed. If 70% of the hours have gone on a stage that is 50% done, billing 70% charges the client for your overrun, and the money won't be there at the end of the stage.
What should a practice do when a stage is running over its hours?
Find the cause first. If the client changed something, agree an additional service. If the design hasn't settled, a director needs to make a decision. If the estimate was simply too low, finish the stage, absorb the loss and correct the estimate for the next proposal.
Does ERPFlow have timesheets for tracking team time on projects?
Not yet. ERPFlow doesn't have a timer or timesheets today. A project card has a time spent field typed in by hand. Time tracking, including converting tracked time into invoices, is coming soon.
Does ERPFlow have stage budgets or project profitability?
No. ERPFlow has no stage budgets, staff rates or per-project profitability. A practice keeps its hours budget in a spreadsheet, and uses ERPFlow for the project boards, the quote and the stage invoices.