5 min read

Budget hours vs actual hours: tracking a fixed-fee design project

Turn a fixed fee into an hours budget, compare it weekly with real progress, forecast the finish, and know what to do when the hours run ahead.

Last updated November 6, 2026

To track budget hours against actual hours on a fixed-fee design project, turn the fee into an hours budget per stage before work starts, log time against those stages, and compare weekly the hours used with the share of each stage finished. The gap is your early warning, while there's still time to act.

How do you turn a fixed fee into an hours budget?

To turn a fixed fee into an hours budget, divide the fee, less any outside costs, by your average charge-out rate, then hold some of the hours back. Here's an invented example: a design studio agrees a fixed fee of €24,000 with no outside costs, and its team averages €80 an hour.

€24,000 ÷ €80 = 300 hours. The studio holds back 10%, which is 30 hours, as contingency and shares out the other 270.

Stage Budget hours
Concept 60
Developed design 80
Technical drawings 90
Site and handover 40
Allocated 270
Contingency 30
Total 300

The charge-out rate already has your margin built into it, so 300 hours delivers the planned profit. Hour 301 starts eating it. If your stages follow the RIBA Plan of Work, the guide to RIBA stage fees covers the split, and the same method works for marketing agencies and consultants on fixed fees.

What should you compare each week?

Compare hours used with how much of each stage is actually finished. Hours used alone tell you what you've spent, and they say nothing about how far you've got.

Here's the same invented project at week 10:

Stage Budget Actual % complete Earned hours Variance
Concept 60 68 100% 60 −8
Developed design 80 74 75% 60 −14
Technical drawings 90 12 10% 9 −3
Site and handover 40 0 0% 0 0
Total 270 154 129 −25

Earned hours are the budget multiplied by the percentage complete. Variance is earned hours minus actual hours, so a negative figure means you've used more than the progress justifies.

Developed design is the row that misleads. At 74 of 80 hours, it looks 6 hours under budget. It's only 75% done, so it's really 14 hours behind. Ask whoever runs the stage for the percentage complete, and ask them to judge it by what's left to do, since hours spent will flatter it.

How do you forecast where the project will finish?

You can forecast the finish in two ways, and the truth usually lies between them.

Forecast Assumes Sum Hours at finish
Best case Everything from here goes to budget 154 + (270 − 129) 295
On current trend The overrun rate continues 270 × 154 ÷ 129 322

The best case stays inside the 300 hours, with 5 of the contingency left. The trend runs 22 hours past the whole fee, which at €80 an hour is €1,760 of time nobody is paying for. Week 10 is when that's still worth knowing, because 141 budgeted hours of work are still to come.

What do you do when actual hours run ahead of budget?

Find the cause first, because each one has a different answer.

Cause What to do
The client changed the brief Agree an additional fee before doing the work. See additional services
Extra rounds of comments Point to the rounds in your proposal, and charge for more if the agreement allows
Your own rework Absorb it, record it and fix the cause
Senior people doing junior work Hand it down, since the same hours cost more at senior level
The estimate was wrong Absorb it, and correct the figure for your next proposal

For a client-driven change, send the email before you start:

The layout change you asked for on 12 March is outside the agreed brief. It will take about 16 hours, which at €80 an hour comes to €1,280 plus VAT. Please confirm by email and we'll add it as a separate stage.

What should you do when the project ends?

When the project ends, write the final hours for each stage next to the budget and keep the table. After a few projects, you'll have something better than any rule of thumb: you'll know that your concept stage takes 70 hours, not 60.

Those figures are what make the next fixed fee safe to quote. The guides on lump sum vs hourly fees and writing a fee proposal from your own past hours pick it up from there.

Tracking a fixed-fee project in ERPFlow

ERPFlow has no project budgets, rates, per-project costing or profitability, so it can't show a variance or warn you about an overrun. ERPFlow doesn't have a timer or timesheets today. Time tracking, including converting tracked time into invoices, is coming soon.

Here's what you can do today:

  • The project: one Projects board for the job, linked to the customer, with one card per stage. Put the budget in the title, such as "Concept (budget 60 h)".
  • The hours: type them into each card's Time spent. The board list shows the total for the project. There's no split by person, and the time carries no date.
  • The comparison: keep the variance table in a spreadsheet. The cards CSV export gives you each card's Time Spent in whole minutes, with its project name, so you don't need to retype it.
  • The fee: put the fixed fee on a quote and convert it to an invoice at each stage. Every conversion makes a fresh draft of the whole quote, which you edit down to that stage's share. Link the invoice to the project under Linked documents.

FAQ

Budget and actual hours: common questions

Didn't find your answer here? We're happy to help.

Contact us
How often should I compare budget and actual hours?
Weekly, for most fixed-fee projects. A weekly comparison catches an overrun while there's still time to change the plan or raise a scope change. A monthly one usually reports a stage that has already gone wrong.
Should I track hours on a fixed-fee project if the client never sees them?
Yes. A fixed fee doesn't change what the client pays, so the hours are the only way to know whether the project made money. They also give you real figures for pricing the next fixed-fee project.
What is the difference between percent used and percent complete?
Percent used is hours spent divided by hours budgeted. Percent complete is how much of the work is finished. A stage that has used 93% of its hours and is only 75% complete is behind, though it still looks under budget.
Should I tell the client when a fixed-fee project is over budget?
Usually not, unless the client caused it. On a fixed fee, an overrun from your own estimate or rework is your cost. An overrun caused by a changed brief is a scope change, and the client should hear about it before the extra work is done.
Does ERPFlow warn me when a project goes over its hours budget?
No. ERPFlow has no project budgets, so nothing can warn about an overrun. A project shows the total time spent on its cards, and comparing that with a budget is a job for a spreadsheet.