AIA G702 and G703: how the application for payment adds up

G703 holds the line-by-line progress and G702 turns its totals into the amount due. Every column and line explained, with a worked application to check your own figures against.

Last updated November 6, 2026

General information, not tax or legal advice. The rules depend on your country and your situation, so check anything with a tax or legal consequence with your accountant.

AIA G702 and G703 add up in one direction. G703 lists each line of the schedule of values with the work done to date. G702 takes its totals, subtracts retainage and everything already certified, and arrives at the current payment due. If the two sheets disagree, expect the application back.

This guide covers the sums only. AIA's instructions say the forms are copyrighted and can't be reproduced or excerpted without its written permission, so use a licensed copy for the real thing. The descriptions below are in our own words.

What are AIA G702 and G703?

AIA G702 and G703 are the American Institute of Architects' payment forms for US construction contracts. G702 is one page holding the contractor's application and the architect's certificate. G703, the continuation sheet, breaks the contract sum into portions of work following the contractor's schedule of values.

The working order starts with G703. You complete it, carry its totals to G702, sign G702, have it notarised and send both sheets to the architect. The architect certifies the amount or a different one, initialling every changed figure and attaching an explanation. The owner then pays on the certificate.

The line numbers and column letters here come from the 1992 editions, G702-1992 and G703-1992. AIA publishes related forms for other situations, such as G702S for subcontractors and G702CW and G702GMP for cost-of-the-work projects, so check which one your contract names.

How do the G703 columns add up?

The G703 columns give each line of the schedule of values its own running account: what the line is worth, what has been done, what's in storage and what's left.

Column What it holds Where the figure comes from
A, B Item number and description Schedule of values
C Value of the line Schedule of values, with approved change orders added as lines
D Work done up to the last application Last application's D + E
E Work done this period Your measure for the period, including stored materials now installed
F Materials stored but not yet installed What is in store at the period end
G Total completed and stored D + E + F
% Progress on the line G ÷ C
H Balance to finish C − G
I Retainage, only where the rate varies by line That line's rate × its amount

Here's an invented example. A contractor with a $480,000 contract and one approved $12,000 change order prepares application 3, with retainage at 5% throughout.

Line C D E F G % H
1 General conditions $48,000 $16,000 $8,000 $0 $24,000 50% $24,000
2 Sitework and foundations $96,000 $96,000 $0 $0 $96,000 100% $0
3 Framing and roof $144,000 $72,000 $43,200 $0 $115,200 80% $28,800
4 Mechanical and electrical $132,000 $19,800 $26,400 $13,200 $59,400 45% $72,600
5 Finishes $60,000 $0 $0 $6,000 $6,000 10% $54,000
6 Change order 1, extra glazing $12,000 $0 $6,000 $0 $6,000 50% $6,000
Total $492,000 $203,800 $83,600 $19,200 $306,600 62.3% $185,400

Column F is where people slip. Line 4's $26,400 in column E includes $9,000 of equipment that sat in column F on the last application and has now been installed. When material goes in, it leaves F and enters E. Leave it in both and you've billed it twice.

How do the G702 lines add up?

The G702 lines start from the contract sum, pick up the G703 totals and work down to the current payment due. Here is the same application:

Line What it is Arithmetic This application
1 Contract sum as signed From the contract $480,000
2 Approved change orders, net Additions less deductions $12,000
3 Contract sum now Line 1 ± line 2 $492,000
4 Completed and stored to date Column G total $306,600
5a Retainage on completed work Rate × (D + E totals) 5% × $287,400 = $14,370
5b Retainage on stored materials Rate × F total 5% × $19,200 = $960
5 Total retainage 5a + 5b, or the column I total $15,330
6 Earned less retainage Line 4 − line 5 $291,270
7 Certified on earlier applications Line 6 of the previous certificate $202,160
8 Current payment due Line 6 − line 7 $89,110
9 Balance to finish, with retainage Line 3 − line 6 $200,730

Application 2 had $212,800 completed and stored, made up of $203,800 of work and the $9,000 of stored equipment. Retainage on that was $10,640, which gave a line 6 of $202,160, and that figure becomes line 7 here.

Line 8 is what you are asking for this month. Line 9 is everything still to come, including the retainage you've earned but haven't received.

How do you check a pay application before sending it?

A pay application can check itself, because the main figures can be reached two ways. Using the example above:

  • Column totals: the C total equals line 3 ($492,000), and D + E + F equals the G total ($203,800 + $83,600 + $19,200 = $306,600).
  • Line 9: equals the H total plus total retainage ($185,400 + $15,330 = $200,730).
  • Line 8: equals the rise in column G less the rise in retainage since the last application ($93,800 − $4,690 = $89,110).
  • Line 7: equals line 6 of the last certificate as certified. If the architect cut your last application, use the certified figure rather than the one you applied for.

What gets a pay application sent back?

A pay application usually comes back because a figure can't be supported, more often than because of a slip in the adding up.

  • Front-end loading. Weighting the schedule of values towards early items brings cash in sooner, and architects look for it. It also leaves the last lines short of money when you need it most.
  • Change orders that aren't approved yet. Only approved ones belong on line 2 and as lines on G703. Mention pending ones in your covering note.
  • Progress ahead of the site. The architect certifies from site observations, so 80% claimed on a framing line that looks 60% done gets cut.
  • Stored materials without paperwork. Many contracts want invoices, insurance or proof of title before paying for materials, especially ones stored off site.
  • The wrong retainage rate. Rates depend on the contract and the state, and some contracts reduce the rate partway through. The guide to retainage on an invoice covers the rules and how the release gets billed.

G702 and G703 are one format for progress billing, and they only show what you've claimed. To see if you're ahead of or behind your own progress, you need a WIP report.

Keeping AIA pay applications alongside ERPFlow

ERPFlow has no AIA forms, schedule of values or retainage line, so G702 and G703 stay on AIA's own forms. Monthly pay applications on large contracts are beyond what it's built for. If you run a small construction business and only some jobs need them, the rest of the billing record can still sit in ERPFlow.

  • Raise the invoice. If the owner's accounts team wants an invoice as well, make an ordinary invoice with one line for line 8 of the certified application. In the example: "Application 3, period to 31 March 2026, current payment due", quantity 1, price $89,110.
  • Give it their reference. The optional Order number field prints on the PDF, which suits the owner's purchase order or contract number.
  • Keep the paperwork on the record. Attach the certified G702 and G703 to the invoice. Attachments are internal and don't go out with the emailed PDF, so send the forms to the owner separately.
  • Record what arrives. Payments go against the invoice, part payments included, and the invoice shows what is still due.

FAQ

AIA pay applications: common questions

Didn't find your answer here? We're happy to help.

Contact us
Is an AIA G702 the same as an invoice?
Not quite. An AIA G702 is a contractor's application for payment with the architect's certificate on the same form, and the owner pays on the certified amount. Some owners accept the G702 as the billing document and others also want a separate invoice for their accounts team, so ask at the start of the job.
Do I have to use AIA forms for progress billing on a construction job?
No, unless the contract says so. AIA G702 and G703 are common on US construction contracts, but an owner or lender can require a different format, and many smaller jobs are billed on ordinary progress invoices. If the contract names the AIA forms, use a licensed copy.
Can I copy the G702 and G703 into my own spreadsheet?
Not as a copy of the forms. AIA states that its documents are copyrighted and may not be reproduced or excerpted without written permission, and it licenses them through AIA Contract Documents. Keeping your own working sheet of the sums is a different matter, as long as what you submit is the licensed form.
What happens if the architect certifies less than the contractor applied for on a G702?
The owner pays the lower certified amount. AIA's instructions have the architect initial each changed figure on G702 and G703 and attach an explanation. The contractor's next application should then start from the certified figures, because line 7 picks up line 6 of the previous certificate.
Does ERPFlow produce AIA G702 and G703 forms?
No. ERPFlow has no AIA forms, schedule of values or retainage line. A contractor using ERPFlow keeps the pay application on AIA's own forms, and can raise an ordinary invoice for the certified amount and attach the signed forms to it.