How to write an engineering fee proposal

Define the deliverables, estimate hours by grade, choose a fee basis and write down what you've assumed. A worked build-up, a table of fee bases and assumption wording to copy.

Last updated November 6, 2026

General information, not tax or legal advice. The rules depend on your country and your situation, so check anything with a tax or legal consequence with your accountant.

To write an engineering fee proposal, define the deliverables, estimate hours for each by grade, choose a fee basis, and write down what you've assumed and excluded. The client reads the total. Whether you make money on it depends on the assumptions, so they deserve as much care as the number.

What goes in an engineering fee proposal?

An engineering fee proposal states what you'll deliver, on what information, for what fee, under what terms. Each section is there because a dispute starts without it.

Section What it says What goes wrong without it
Scope, by deliverable Calculations, drawings, reports, inspections "Structural design" means everything to a client
Exclusions Geotechnical work, surveys, temporary works, other disciplines You inherit the gaps between consultants
Information from others Survey, architect's drawings, loads, by when You wait, and the programme becomes your fault
Fee and basis Amount, lump sum or time, and what it's fixed against Nobody knows what happens when things change
Rates for extra work Hourly rates by grade, valid to a date Each extra becomes a negotiation
Expenses Included, or charged at cost Travel and printing queries on every invoice
Programme Your dates, tied to receiving the information Dates read as promises regardless of inputs
Payment stages What triggers each invoice You fund the job until the end
Insurance and liability Professional indemnity cover, any cap on liability The client's lawyer writes this part for you
Statutory roles In the UK, whether you take CDM 2015 duties such as principal designer An assumed role, unpriced
Terms Your own, or a named form Two sets of terms and no clear winner

Standard forms save a lot of drafting. In the US, EJCDC publishes owner and engineer agreements, including E-500. Internationally, many consultants use FIDIC's White Book. Have a lawyer or your insurer look at anything amended.

Which fee basis should an engineer use?

The right fee basis depends on how well the scope is defined and who should carry the risk of it changing.

Basis Use when Risk sits with Watch out for
Lump sum The scope is clear and you've done similar work Engineer Scope creep, unless assumptions are tight
Time charge with a cap The scope will develop, but the client needs a limit Shared Say whether the cap can move, and when you'll warn them
Time charge, no cap Investigations, expert work, unknown problems Client Clients want regular reports of hours
Percentage of construction cost The client expects it and the cost is well known Shared Name the cost figure and when it's fixed
Unit rates Repeated items, such as per inspection or per test Shared Quantities can drift, so estimate them

The guide to lump sum vs hourly fees goes further into the first two. Mixed bases are common: a lump sum for design, and unit rates for site inspections.

How do you estimate the hours for an engineering fee?

Estimate the hours for an engineering fee deliverable by deliverable, split by grade, because a principal's hour and a technician's hour cost very different amounts. Here's an invented example: a structural engineer pricing a three-storey extension, at invented rates of €110 for a principal, €85 for a senior engineer and €60 for a technician.

Deliverable Principal h Senior h Technician h Cost
Site visit and review of the existing structure 4 8 0 €1,120
Scheme design and calculations 6 30 12 €3,930
Detailed design, calculations and drawings 6 44 40 €6,800
Building control submission and replies 2 10 6 €1,430
Site inspections: 6 visits at 3 hours 0 18 0 €1,530
Queries during construction 0 12 4 €1,260
Total 18 122 62 €16,070

A 10% allowance for risk adds €1,607, making €17,677. Round it to a lump sum of €17,700, and split it where the work falls:

Payment stage Work it covers Cost Fee
A: on issue of scheme design First two rows €5,050 €5,500
B: on issue of detailed design to building control Next two rows €8,230 €9,100
C: monthly across site inspections Last two rows €2,790 €3,100
Total €16,070 €17,700

Your rates need to carry overheads and profit, and the guide to calculating a charge-out rate shows how. Past jobs are the best check on the hours. The method in writing a fee proposal from past hours works just as well for engineering.

What assumptions should an engineering fee proposal state?

An engineering fee proposal should state every assumption that, if wrong, would change your hours. Wording to adapt:

This fee assumes a steel frame on the existing foundations, subject to the trial pits being provided by others before scheme design starts. It includes six site inspections of up to three hours each and one round of revisions after each drawing issue. Further visits or revisions are charged at the rates in section 6, and we'll tell you before they arise. Geotechnical investigation, temporary works design, connection design by the fabricator and all building services are excluded. Our programme runs from the date we receive the architect's general arrangement drawings and the survey.

The two limits people forget are revisions and site visits, because both feel small when you're writing the proposal and neither is small when the job runs badly. Connection design and temporary works are worth naming too: if nobody says who does them, the question arrives on site.

When do you not give a price at the proposal stage?

You don't give a price at the proposal stage when a public client selects on qualifications first. Under the US Brooks Act, federal agencies select architecture and engineering firms on qualifications, and then negotiate compensation they determine is fair and reasonable with the most highly qualified firm. If that fails, they move to the next firm. The agency weighs the scope, complexity, professional nature and estimated value of the services.

Many states have their own versions for public work, so read the request carefully, since a submission may be expected to leave price out. Prepare your build-up anyway. You'll need it the moment negotiations start, and a table like the one above is what lets you explain a number you can defend.

Sending an engineering fee proposal from ERPFlow

ERPFlow has no estimating sheet, staff rates or project budgets, so the hours build-up stays in a spreadsheet. ERPFlow can handle the priced offer and everything after it:

  • The offer. A quote with one line per payment stage, with tax set per line, goes out as a PDF in any of 19 languages, with the email recorded on it. The quote's notes print on the PDF, which suits a short list of assumptions. Keep the full scope in your own document and send it separately, because attachments on a quote are internal.
  • Your rates. A service holds each hourly rate with its tax, ready for any time-charged extras.
  • Acceptance. There's no e-signature or online acceptance. You mark the quote accepted by hand and can attach the signed proposal to it.
  • Billing by stage. Choose Convert to invoice when a stage falls due. Each conversion is a fresh draft invoice of the whole quote, so remove the other stages' lines before issuing. The two documents stay linked, and the progress billing guide covers how to set the stages up.

FAQ

Engineering fee proposals: common questions

Didn't find your answer here? We're happy to help.

Contact us
What is the difference between an engineering fee proposal and a quote?
Scope is the difference. A quote prices a defined item. An engineering fee proposal also defines the work itself, including deliverables, assumptions, exclusions, information needed from others and the terms, because the service is usually still taking shape when it is priced.
Should an engineering fee proposal include site visits?
Yes, as a stated number. An engineering fee proposal that promises site inspections without a limit leaves the engineer carrying the risk of a slow or troubled build. State the number of visits, the length of each, and the rate for any more.
Can an engineer charge a percentage of construction cost?
Yes, if the contract says so. A percentage fee must name which cost figure it applies to and when that figure is fixed. It also rewards a higher build cost and can pay badly when a cheap building is hard to engineer, so many engineers prefer a lump sum or capped time charge.
Do US federal agencies choose engineers on price?
No, not at the selection stage. Under the Brooks Act, US federal agencies rank architecture and engineering firms on qualifications, then negotiate a fair and reasonable fee with the most highly qualified firm, moving to the next firm if they can't agree. Many states have similar rules for public work.
Does ERPFlow have a fee estimating tool for engineers?
No. ERPFlow has no estimating sheet, staff rates or project budgets. An engineering firm builds the fee up in a spreadsheet, then uses an ERPFlow quote to send the priced offer and convert it into invoices stage by stage.